M+W U.S., Inc. & GLOBALFOUNDRIES CONSTRUCTION SCHEDULE

6.15.09 - Site Work Start
7.24.09 - Groundbreaking
8.21.09 - Building Permits
9.9.09 - First Concrete
12.5.09 - First Trusses
Clearing, grubbing and grading operations have been initiated after receipt of Final Site Plan Application approvals from the Towns of Malta and Stillwater.
The official groundbreaking ceremony for Fab 8, Module 1 was held with Governor Paterson and other high ranking state, local and GLOBALFOUNDRIES officials.
The Town of Malta issued the first building permits for the project including site utilities and foundations for the Fab/Spine and Central Utilities Building.
The initial 2,500 Cubic Yards foundation pour at the Fab was started fully utilizing materials from the on-site concrete batch plant.
The first pair of steel trusses were installed in the Fab. Each truss weighed 45 tons
and was placed in parallel by a single 300 ton crane. The trusses span half the
distance between the east and west Fab exterior walls.
1.27.10 - CUB Topping Off
2.15.10 - Foundry Opens
3.24.10 - Admin Foundations
4.20.10 - Expansion Approved
4.26.11 - Fab 8 Meeting
The last steel beam was put in place on the Central Utility Building marking the first building component of Fab 8 to celebrate a 'topping off.'
The Foundry, Fab 8's on-site restaurant, opened to serve breakfast, lunch and dinner to the work crews.
The initial pouring of the Administration Building foundations starts the last major component of Fab 8.
The Town of Malta Planning Board approves the expansion of the Fab 8, Module 1 Cleanroom from 210,000 to 300,000 SF.
Fab 8 Project Review / Neighborhood Meeting. Please click on the Download Special Construction Notices! link above for details.

Project Overview

M+W U.S., Inc. is designing and building the most advanced semiconductor manufacturing complex in the world for GLOBALFOUNDRIES. The Fab 8, Module 1 facility is located at the Luther Forest Technology Campus in the Towns of Malta and Stillwater, Saratoga County, New York. GLOBALFOUNDRIES Fab 8, Module 1 is the first of three potential Semiconductor Manufacturing facilities proposed for the Luther Forest Technology Campus (“LFTC”). Fab 8, Module 1 consists of four major buildings including the wafer fabrication building (“Fab”), the Central Utility Building (“CUB”), the Spine or Fab technical support building, and the Administration Building. Additionally, there will be an Electric Substation Building and a Hazardous Production Materials warehouse, as well as other miscellaneous structures and utility yards. GLOBALFOUNDRIES is striving to achieve LEED Gold Certification for the Administration Building and for the Fab.

The realization of this project will be the crowning achievement in the continued development of New York's Tech Valley as a pre-eminent location for technological breakthroughs not only in the field of semiconductors but in nanotechnology, bio-technology, pharmaceuticals and alternative energy as well.

M+W U.S., Inc. is proud to be a leader in this effort and shares this website in order to provide information and the excitement of constructing this most important project with the local and world-wide communities.

Current Construction Activity and Status

The site development phase for the construction of GLOBALFOUNDRIES Fab 8, Module 1 began on June 15, 2009 with final grading/roadwork activities nearing completion. Temporary structures such as the Concrete Batch Plant, Construction Manager’s Office, the Foundry and workers' parking have been completed. Foundations at the Fab, Administration Building, Spine and CUB are completed with all concrete manufactured on-site. Roof and interior building steel has been completed at the Fab, Spine, Administration Building and CUB. The Wastewater Pump Station, Electrical Service Building and related high voltage yards are completed. The Phase 2 expansion of the Fab commenced at the end of August with foundation work and steel erection completed. The current phase of construction includes the completion of interior architecture systems and installations of HVAC, plumbing, fire protection and electrical systems and components. As of March 2011, the building portion of the project is 75% complete.

Please continue to check back for more details, information and photos.

Construction Schedule

The Fab, Spine, Administration Building and CUB envelopes have been enclosed. The Fab Phase 2 expansion started at the end of August with foundations and steel structure completed and envelope completed in the late spring. Tool deliveries will be increasing throughout the summer, peaking in the fall. The construction project is expected to take approximately two years to complete and an additional 12 to 18 months to ramp up to full operating mode, with volume production anticipated in early 2012.

Notices

The Town of Malta has authorized extended hours for construction work. The new hours are Monday through Friday from 6:00 AM to 8:00 PM for exterior construction and from 6:00 AM to 11:59 PM for interior work. Saturday work hours are from 7:00 AM to 6:00 PM for exterior construction and from 6:00 AM to 11:59 PM for interior work.

Fab 8, Module 1 Architectural Drawings

(Please click on each drawing to see a larger version.)

 

Deliveries and Traffic Impacts

The construction and management work force has continued to ramp up during the summer with 1,000 workers anticipated on site by September. Delivery of steel trusses and pre-cast waffle slabs will continue throughout the summer and into fall. In addition, mechanical and electrical equipment, steel trusses and pre-cast concrete deliveries will be increasing throughout the summer. Deliveries to the site are authorized only through the Stone Break Road entrance to the site from Route 9.

Fab 8 Construction Hotline

M+W U.S., Inc., GLOBALFOUNDRIES and the Towns of Malta and Stillwater are taking steps to make sure the construction of Fab 8, Module 1 will have as little impact on the surrounding community as possible.

To help ensure fast and effective communications with the community, we have established a process to receive and respond to construction-related concerns.

If you have a comment, complaint, or issue related to construction, please call the Fab 8 Construction Hotline at (518) 899-0127.

For all emergencies, please call 911.

Complaint Process

Art Kaplan, Fab 8's Community Relations Manager (CRM) has been identified as the point of contact for construction related issues. During the approved project working hours of Monday through Saturday 7 a.m. to 6 p.m. or when approved, extended working hours, your call will be answered within an hour. During non-working hours, you may leave a message with the M+W U.S., Inc. answering center which will be documented for direct follow-up by the CRM.

If the issue is noise related you will be contacted within 24 hours to record the complaint. All calls will be documented in writing through a Project Issues Form and every inquiry will receive a response once the issue is discussed, reviewed.

For all emergencies, please call 911. 